Monday, August 3, 2015 — Week Seventeen

by

Chad from Wesson (our builder) spent much of his day building the window seat at the end of the master suite hallway. It has a hatch in the top so we can use the interior for storage. Lynda will be making a cushion for the seat.

Window seat in master suite hallway.

Window seat in master suite hallway.

 

The guys also completed repairs on a crack in the ceiling of the quilt studio and thoroughly cleaned up the areas of new construction, all in preparation for the return of the painters later this week.

In addition, the new toilet in the guest bathroom is now functional, replacing the old one which had seen better days.

The new ceiling medallions are now on hand so the electrician can install the replacement ceiling fixtures in the living room.

Medallions for ceiling fixtures in living room.

Medallions for ceiling fixtures in living room.

 

We are awaiting delivery of two pocket doors for the addition. The first two that we received were warped, so new ones had to be ordered.

Saturday, August 1, 2015 — Week Sixteen

by

The electrician worked on Saturday and almost finished everything.

He connected and tested a new phone line for the bedroom, added a quad outlet near my workbench in the garage, installed a cable TV box in the bedroom, and installed the bedroom ceiling fan.

Bedroom ceiling fan.

Bedroom ceiling fan.

 

He removed the old ceiling fan in the living room but did not have a new ceiling medallion. So for the moment, we have this instead of our new fan:

The new ceiling fan in the living room will go here.

The new ceiling fan in the living room will go here.